Advice please on connecting a new house

15 posts in this topic

When we first moved ino to 30 sq m 2 Bed Bungalow, we were on a Temp Supply from Crown Asia and it was absolute crap!

 

The developer was in no rush to get the Buildling Permit completed by then getting the Occupancy Permit

So I just contacted VECO directly and they sorted it out.

All the details on the VECO website:-

veco_logo.jpg

residentialbanner_wider.jpg

Customers applying for electric service for domestic purposes in a single-family dwelling unit, individually metered apartments which are incidentally but not primarily used as rooming or boarding houses belongs to Residential category.

4 Guide Questions 1.Is your house/ building within 30 meters away from the nearest VECO pole with secondary line?

Check if the nearest VECO pole already has existing customers connected to it. If NO, you may be required to apply for a secondary line and/ or pole extension, and may need to put up a deposit for such. Please see our Customer Retail Services Department (CRSD) at VECO Full Service Center, 3rd Level, SM City Cebu or at VECO Talisay Full Service Center, South Road, N. Bacalso Ave., Bulacao Talisay City.

2.Does your application:

  • exceed 8,000 Watts in total?
  • need a three-phase supply?, OR
  • require a service voltage other than 220 Volts? (When in doubt, you can consult a licensed electrical practitioner)

If YES, you need to apply for a separate transformer and will be required to put up a deposit for such. Please see our Customer Retail Services Department (CRSD).

3.Do you have a previous connection with VECO that was disconnected and has unpaid accounts?

If YES, you will be required to settle all previous unpaid bills and arrears. You can pay directly through any of our collection offices.

4.Have you ever been apprehended by VECO or is currently being charged in court by VECO for electricity pilferage?

If YES, VECO has the legal right to deny service to any person or entity who has violated R.A. 7832 (Anti-Pilferage Act).

STEPS IN APPLYING FOR AN ELECTRIC SERVICE

 

You may apply for an Electrical Permit at the following offices depending on the location of the premises sought to be energized:

OFFICE

TELEPHONE NUMBER

Cebu City - City Engineer's Office ........................254-9872

Mandaue City - City Engineer's Office .................344-0608

Talisay City - City Engineer's Office......................273-7768

Consolacion - Municipal Engineer's Office ........344-1239, 344-1236/ 37 local 110

Lilo-an - Municipal Engineer's Office ..................564-3784

Minglanilla - Municipal Engineer's Office .....273-7453

Naga - City Engineer's Office ................................272-6651 or 272-6655

San Fernando - Municipal Engineer's Office ......488-9694

spacer.gifspacer.gif

Start Servicespacer.gif

Stop Servicespacer.gif

Application Checklistspacer.gif

spacer.gif

Added Value Servicesspacer.gif

 

Veco Metering Standard

 

simple-metering.jpg

SIMPLE METERING SET-UP

Estimated Labor Cost: Php1,500

Share this post


Link to post
Share on other sites

Thanks for the replies. The consensus seems to be that I am being shafted and should refuse. I am in a reasonably strong position in that I hold a 10% retention of the purchase price which I have already told them I won't pay until all the site facilities (like the pool, clubhouse and landscaping) are finished and that I intend to deduct the 30,000 I paid out to get the water and power connection process started.

 

We are actually the second house to be occupied, although the first on this phase. Others are due very soon, also all by foreigners, and as I cannot believe they will accept these charges either, I intend to co-ordinate the refusals. I have been told by the developers that all the homes will face these costs. Lets see! I will talk to the other existing owners, who we rarely see, to find out what their experience has been.

 

31,000of the 54,000 is described as a "bill deposit". This is said to be refundable whenever we sell the property (probably never in my lifetime) but there is no mention of them paying any interest on them holding my money for an extended period. This seems to me to have nothing to do with the actual installation but Veco using their monopoly position to get their bills paid in advance. This attitude offends someone like me who is used to be trusted and has never defaulted on a bill. I intend to tell Veco this and see what alternative arrangements can be made. Not that I expect to get too far!

 

The remaining charges are for the installation and I definately intend to refuse these, as I believe it is the responsibility of the developers to provide power to the house. It is mine to pay for it.

 

If I had built this myself then of course I would have no choice, but part of the comfort of buying in a sub division is in giving all these responsibilities, and seeing all the costs summarised in the one purchase price.

 

Any more information gratefully received. I will keep you posted (no pun intended) of developments as they occur.

Share this post


Link to post
Share on other sites

Yesterday I visited Veco at SM and they confirmed the charges but said this was a matter between me and the developers, they don't care to whose account they are held so long as they get paid!

 

I was told that the 31,000 "bill deposit" was based upon the "load calculations" made by the engineer. This is also interest bearing and is repaid whenever supplies are terminated. However they could not advise what the rate of interest will be.............. "it will be on your annual statement, Sir!". I was also told that the load can be recalculated, and I will surely do that as I guess that is for the whole Phase of houses!

 

The connection charges I will just refuse, as I expect the developers to provide a service to the house.

 

If anyone has anymore comments or information it will be gratefully received.

Share this post


Link to post
Share on other sites

Yesterday I visited Veco at SM and they confirmed the charges but said this was a matter between me and the developers, they don't care to whose account they are held so long as they get paid!

 

I was told that the 31,000 "bill deposit" was based upon the "load calculations" made by the engineer. This is also interest bearing and is repaid whenever supplies are terminated. However they could not advise what the rate of interest will be.............. "it will be on your annual statement, Sir!". I was also told that the load can be recalculated, and I will surely do that as I guess that is for the whole Phase of houses!

 

The connection charges I will just refuse, as I expect the developers to provide a service to the house.

 

If anyone has anymore comments or information it will be gratefully received.

 

 

 

 

 

you said it yourself it dont matter to veco WHO pays ... when you purchaced your house you expected there to be power and water and if there is not well your the one wronged... stay firm

Share this post


Link to post
Share on other sites

veco_logo.jpg

residentialbanner_wider.jpg

Customers applying for electric service for domestic purposes in a single-family dwelling unit, individually metered apartments which are incidentally but not primarily used as rooming or boarding houses belongs to Residential category.

4 Guide Questions 1.Is your house/ building within 30 meters away from the nearest VECO pole with secondary line?

Check if the nearest VECO pole already has existing customers connected to it. If NO, you may be required to apply for a secondary line and/ or pole extension, and may need to put up a deposit for such. Please see our Customer Retail Services Department (CRSD) at VECO Full Service Center, 3rd Level, SM City Cebu or at VECO Talisay Full Service Center, South Road, N. Bacalso Ave., Bulacao Talisay City.

2.Does your application:

  • exceed 8,000 Watts in total?
  • need a three-phase supply?, OR
  • require a service voltage other than 220 Volts? (When in doubt, you can consult a licensed electrical practitioner)

If YES, you need to apply for a separate transformer and will be required to put up a deposit for such. Please see our Customer Retail Services Department (CRSD).

3.Do you have a previous connection with VECO that was disconnected and has unpaid accounts?

If YES, you will be required to settle all previous unpaid bills and arrears. You can pay directly through any of our collection offices.

4.Have you ever been apprehended by VECO or is currently being charged in court by VECO for electricity pilferage?

If YES, VECO has the legal right to deny service to any person or entity who has violated R.A. 7832 (Anti-Pilferage Act).

STEPS IN APPLYING FOR AN ELECTRIC SERVICE

 

You may apply for an Electrical Permit at the following offices depending on the location of the premises sought to be energized:

OFFICE

TELEPHONE NUMBER

Cebu City - City Engineer's Office ........................254-9872

Mandaue City - City Engineer's Office .................344-0608

Talisay City - City Engineer's Office......................273-7768

Consolacion - Municipal Engineer's Office ........344-1239, 344-1236/ 37 local 110

Lilo-an - Municipal Engineer's Office ..................564-3784

Minglanilla - Municipal Engineer's Office .....273-7453

Naga - City Engineer's Office ................................272-6651 or 272-6655

San Fernando - Municipal Engineer's Office ......488-9694

spacer.gifspacer.gif

Start Servicespacer.gif

Stop Servicespacer.gif

Application Checklistspacer.gif

spacer.gif

Added Value Servicesspacer.gif

 

Veco Metering Standard

 

simple-metering.jpg

SIMPLE METERING SET-UP

Estimated Labor Cost: Php1,500

Share this post


Link to post
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!


Register a new account

Sign in

Already have an account? Sign in here.


Sign In Now
Sign in to follow this  
Followers 0

  • Commercial Banner Advertisers

  • Adsbygoogle

    Advert

  • Recently Browsing   0 members

    No registered users viewing this page.



  • Donation Goals

    Modifications, Applications, & Plugins

    Purchase and renewal costs for themes and various features added to the forums.

    $30 USD added to cover PayPal fees.



    $240.27 of $280.00 goal reached.
    Donate Now
    Yearly Hosting Fees

    Yearly web hosting fees, $75 USD / month.

    $30 USD added to cover fees.



    $439.72 of $930.00 goal reached.
    Donate Now
    Software Licensing Renewal Fees

    This goal is 100% funded. Please choose one of the others to support.

    $50 USD every six months for software licensing.

    $15 USD added to cover PayPal fees.



    $115.08 of $115.00 goal reached.
    Donate Now
  • Donation Stats

    • Total Donations
      $795.07
    • Total Fees
      $29.93
    • Total Goals
      $1,325.00
    • Still Needed
      $529.93

    • $795.07 of $1,325.00 goal reached.
  • Adsbygoogle

    Advert